Contractor Entitlement Navigator©:

Extension of Time, Cost, and Reasonable Profit under the FIDIC 1999 General Conditions

FIDIC Red Book 1999: Contractor Entitlements | SCCSI
S C C S I
FIDIC Red Book (1st Ed. 1999) sccsinternational.org
Contractor Entitlement Navigator: Extension of Time, Cost, and Reasonable Profit under the FIDIC 1999 General Conditions
Filter sub-clauses by entitlement category. Asterisk indicates a conditional or non-standard entitlement (see footnote). Valuation, procedural, and termination-payment provisions (SC 12.3, 13.3, 19.6, 20.1) are excluded.
SELECT
ENTITLEMENT
EOT+Cost
+Profit
EOT+Cost
Cost+
Profit
Cost only
EOT only
EOT + Cost + Reasonable Profit
7 sub-clauses
EOT+Cost+Profit
EOT+Cost
Cost+Profit
Cost
EOT