Select Page

Hallings Wharf Studios Case Navigator©:

Remediation contribution order in the amount of £ 3,682,997.78,  alternative scheme argument and litigation-cost recoverability.

The matter is reported as the first remediation contribution order obtained on an application by central Government.

Secretary of State for Housing, Communities and Local Government v EDR Builders Ltd and Hollybrook (UK) Ltd (Hallings Wharf Studios), LON/00BB/BSB/2024/0011

Hallings Wharf Studios: Case Navigator | SCCSI
SCCSI
Presented by
Society of Construction Claims Specialists International
sccsinternational.org
Case Navigator · Building Safety Act 2022

Hallings Wharf Studios, central Government secures its first remediation contribution order

Secretary of State for Housing, Communities and Local Government v EDR Builders Ltd and Hollybrook (UK) Ltd (Hallings Wharf Studios), LON/00BB/BSB/2024/0011

The dispute was about who should bear the cost of remediation at Hallings Wharf Studios and whether the Secretary of State could recover 3,682,997.78 pounds by way of a remediation contribution order under the Building Safety Act 2022. The First-tier Tribunal (Property Chamber) made the order sought, and the case is reported as the first such order obtained on an application by central Government. Click any node to open it. The story runs in order, from the parties to the practical lessons.

Result The Secretary of State (applicant) substantially won. The tribunal made a remediation contribution order in the sum of £3,682,997.78, but not for the Secretary of State's litigation costs.
TribunalFirst-tier Tribunal (Property Chamber)
ApplicantSecretary of State for Housing, Communities and Local Government
RespondentsEDR Builders Ltd and Hollybrook (UK) Ltd
Procedural settingApplication for a remediation contribution order under the Building Safety Act 2022
Order made£3,682,997.78
ImportanceReported as the first remediation contribution order obtained on an application by central Government
Court finding Respondent argument addressed Practical point
1
Orientation
What the case is about, in one minute

This case note concerns an application for a remediation contribution order under the Building Safety Act 2022. The Secretary of State sought an order against EDR Builders Ltd and Hollybrook (UK) Ltd in relation to Hallings Wharf Studios.

The tribunal made the remediation contribution order in the sum of £3,682,997.78. The available reports say this was the first such order obtained on an application by central Government, and that the tribunal addressed both the alternative scheme argument and the recoverability of litigation costs, while not awarding litigation costs to the Secretary of State.

Why it matters

The reported decision shows that major disputes under the Building Safety Act 2022 may turn on who pays, what sum is recoverable and how the tribunal deals with arguments that the remedial works could have been done more cheaply.

2
Parties and procedural setting
The Secretary of State as applicant, EDR and Hollybrook as respondents
ApplicantSecretary of State for Housing, Communities and Local Government
RespondentsEDR Builders Ltd and Hollybrook (UK) Ltd
TribunalFirst-tier Tribunal (Property Chamber)
Procedural settingApplication for a remediation contribution order under the Building Safety Act 2022
3
The dispute and the order
Hallings Wharf Studios and a reported order of 3,682,997.78 pounds

The case was Secretary of State for Housing, Communities and Local Government v EDR Builders Ltd and Hollybrook (UK) Ltd (Hallings Wharf Studios), LON/00BB/BSB/2024/0011.

The Secretary of State sought to make EDR Builders Ltd and Hollybrook (UK) Ltd bear the cost of remediation at Hallings Wharf Studios. The tribunal made a remediation contribution order under the Building Safety Act 2022 in the sum of £3,682,997.78, and the available reports say this was the first remediation contribution order obtained on an application by central Government.

4
The key issues
Four questions the tribunal had to address
OrderWhether the tribunal should make a remediation contribution order under the Building Safety Act 2022
QuantumWhether the sum of £3,682,997.78 should be recoverable
Alternative schemeHow the tribunal dealt with the argument that the works could have been carried out more cheaply
Litigation costsHow the tribunal dealt with the recoverability of litigation costs
5
The applicant's case
Make the order in the claimed sum

The Secretary of State's position was that a remediation contribution order should be made against the respondents. The application sought recovery of £3,682,997.78 under the statutory regime.

The reported case note also records that the defect position was effectively conceded by reference to Edgewater (Stevenage) Ltd v Grey GR Limited Partnership [2026] UKUT 18 (LC). On that footing, the live dispute appears to have centred on financial responsibility for remediation rather than on whether the defects fell within the statutory scheme.

6
The respondents' case
Cheaper works and recoverability points were raised

The available reports do not preserve a full pleaded defence from either respondent. What they do preserve is that the tribunal dealt with an argument that the remedial works could have been carried out more cheaply, described as the alternative scheme argument.

The same reports also record that the tribunal dealt with the recoverability of litigation costs. That indicates the respondents challenged at least part of the amount claimed and the scope of sums recoverable on the application.

7
The tribunal's findings
Order made; quantum and recoverability issues addressed

The tribunal made a remediation contribution order in the sum of £3,682,997.78. The available reports say the tribunal gave guidance on recoverability where a respondent argues the works could have been carried out more cheaply.

Alternative scheme argumentAddressed

The available reports say the tribunal dealt with the argument that the remedial works could have been carried out more cheaply. The preserved sources do not contain the tribunal's exact wording on that point.

Litigation costsAddressed

The reports also say the tribunal dealt with the recoverability of litigation costs. The preserved sources do not contain the tribunal's exact wording on that point either.

The reports further record that the relevant defects were effectively conceded by reference to Edgewater. That suggests the tribunal was dealing with responsibility for payment and recoverable sums on the footing that the defect issue was no longer the central contest.

Practical point

On the available reports, the dispute had moved from defect existence to financial consequence. That is where the reported arguments on alternative schemes and litigation costs sit.

8
The decision and who won
Order made; the Secretary of State succeeds

The tribunal made a remediation contribution order in the amount of £3,682,997.78, but not for the Secretary of State's litigation costs.

The practical result was that the Secretary of State succeeded in obtaining what is reported to be the first remediation contribution order secured by central Government, but did not recover litigation costs.

Who won

The Secretary of State substantially won. The tribunal made the remediation contribution order in the sum of £3,682,997.78 against the respondents, but not for litigation costs.

9
Practical takeaways
For building-safety recovery disputes under the 2022 Act
LessonWhat to do
Central Government can obtain an RCOThe available reports describe Hallings Wharf as the first remediation contribution order obtained on an application by central Government.
Cheaper alternative arguments matterA respondent may argue that remedial works could have been carried out more cheaply, but the tribunal can still address recoverability and make a substantial order.
Costs can become part of the main disputeLitigation-cost recoverability may be argued alongside the principal remediation sum rather than treated as an afterthought.
The contest may shift to quantumWhere defects are effectively conceded, the main fight may move to responsibility, quantum and recoverable heads of claim.
Legal disclaimer
This navigator is provided for educational and professional development purposes only and does not constitute legal advice. It is based on the companion case note, "Hallings Wharf Studios, central Government secures its first remediation contribution order". It is not a substitute for the full tribunal decision, the statutory materials, the governing law or the specific facts. Always consult qualified professionals before acting. SCCSI and its contributors accept no liability for reliance on this material.
Build your expertise in construction adjudication, NEC and FIDIC contract administration with SCCSI. This navigator is a module from the Society of Construction Claims Specialists International's Construction Claims and Contracts Certification Programmes. sccsinternational.org

Apply To Become An ECCCS/ECCDA/ECCCA/ECCCM